Updated Schedule - Roadway Resurfacing and Repairs Project

Updated Schedule - Roadway Resurfacing and Repairs Project

E & B Paving, faced with material delay and weather, are working hard to wrap the Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1.  Over the next few weeks, E & B Paving will be completing the project in accordance with the following UPDATED tentative schedule:

November 4th - November 21st: Pendleton Avenue (from Railroad Crossing to SR 67) Trench, Mill & Install Guardrail and Sign  *Expect lane restrictions during construction as well as extended road closure during this time. *Work to be conducted during day hours.

November 22nd:  Pendleton Avenue (from Railroad Crossing to SR 67)   Paving *Work to be conducted during day hours.

November 28th & 29th:  Pendleton Avenue (from Railroad Crossing to SR 67)   Permanent Markings & Sign/Barricade Removal *Work to be conducted during day hours.

Please note that all dates are weather dependent.  Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires.  Further, local residents may experience limited inconvenience the day of the scheduled paving. 

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS