Updated Schedule - Roadway Resurfacing and Repairs Project

Updated Schedule - Roadway Resurfacing and Repairs Project

The Town of Pendleton is very excited that its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1 is well underway.  Over the course of the next few months, E & B Paving will continue improving several of our local roads according to the following UPDATED tentative schedule:

August 30th - September 1st:  State Street (Mill and Pave from Main Street to Railroad Viaduct)   *Work to be conducted during night hours.                       

September 7th – October 18th:  Pendleton Avenue (from Railroad Crossing to SR 67)   *Expect lane restrictions during construction as well as extended road closure roughly three (3) weeks during this time period. *Work to be conducted during day hours.

October 19th - October 20th: Water Street, State Street & Pendleton Avenue (install permanent markings) *Work to be conducted during day hours.

Please note that all dates are weather dependent.  Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires.  Further, local residents may experience limited inconvenience the day of the scheduled paving. 

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS